1. You are in the process of performing Develop Schedule process to determine planned start and finish dates for project activities. Which of the following inputs will be helpful in this process?
a) Activity attributes, project scope statement, and activity list
b) Activity list, activity attributes, and schedule data
c) Project calendar, requested changes, and schedule data
d) Work performance information, schedule baseline, and performance reports

2. You are managing a project to develop an emergency brake to an upcoming new model of RV. In your project, you have to complete building a prototype before testing can begin. This is an example of:
a) Mandatory dependency
b) Discretionary dependency
c) External dependency
d) Preferred logic

3. Your company has decided to outsource one of its IT product developments to ABC IT Services through a contract. You clarify the structure and requirements of the contract so that mutual agreement can be reached prior to signing the contract. Which of the following statements on procurement negotiations are correct?
a) You have to discuss technical and business management approaches, proprietary rights, overall schedule, payments, and price.
b) At the end of the procurement negotiations, you will have a contract document executed by both buyer and seller.
c) The project manager is the lead negotiator on the procurement.
d) Final contract language will reflect all agreements reached.

4. Your project, you need to verify whether deliverable meet requirements and product acceptance criteria. For this purpose, which of the following would you rely on?
a) Inspection
b) Expert judgment
c) Observations
d) Focus groups

5. The Scope Management Plan is an important component of the Project Management Plan since it provides direction on how the project scope will be managed throughout the project life cycle. The Scope Management Plan documents:
a) Which product requirements will be incorporated
b) How project scope will be defined, developed, controlled, and verified
c) Which stakeholders are most critical for defining the project scope
d) High-level project scope deliverables

6. You would like to obtain information, quotations, bids, offers, or proposals from sellers as part of the Conduct Procurements process. In this process, which of the following is the most critical?
a) Determine whether a product should be purchased or manufactured in-house.
b) Ensure that prospective sellers clearly understand the technical and contract requirements.
c) Clarify the structure and requirements of the contract.
d) Prepare an independent estimate to verify the proposed price structures of the sellers.

Friday 7 October 2016

What is Organizational Process Assets In PMBOK 5th Edition

You will find Enterprise Environmental Factors (EEFs) and Organizational Process Assets (OPAs) very frequently while going through the PMBOK5th edition and therefore firm understanding of the topics is required. Here we will discuss the Organizational Process Assets.
Asset: Any tangible or intangible thing that can be owned or controlled to produce value for us is called an Asset for us. For example my house which I use to live is an asset for me, and so my car is which I use to commute etc.
ID-10065615

Similarly an organization has assets in terms of process policies and knowledge base which becomes mature with the time. Organization invests in creating all these process, policies and knowledge bases so that it can help the organization wherever it is needed and thus called Organizational Process Assets.
Let me give a real example: One of my friend in my last organization was assigned a finance related project and he had to develop a detailed risk management plan. He was not experienced enough in doing that and therefore he approached me. I asked him to go to our company’s knowledge base and get one template for the same and then develop his own. And after few days I saw his name in one of the best PM of that quarter. See how helpful the knowledgebase can be for anyone who needs it and that’s why we call it Organization Process Assets.
Organizational Process Assets has important role in project’s outcome and with the time it grows and becomes more and more mature.
As per PMBOK the Organizational Process Assets is divided in two categories
  1. Processes and procedures
  2. Corporate knowledge base